Consumers Energy plans $225M in Mich. system upgrades
Jackson — Consumers Energy plans to spend nearly $225 million this year to upgrade its Michigan natural gas system, including 27 projects in Oakland, Wayne and Macomb counties.
The unit of Jackson-based CMS Energy Corp. says Monday work includes infrastructure replacement projects; upgrades to compressor and pressure regulation facilities; and upgrades to accommodate new business and residential customers.
The utility says $75 million will be spent to complete 60 improvement projects and replace an additional 86 miles of pipe. Work also includes 11 projects in Ingham, Jackson and Lenawee counties; and 11 projects in Barry, Eaton, Kalamazoo and Van Buren counties.
About $31 million will accommodate more than 10,000 expected new business customers. About $35 million will add 146 miles of lines for more than 2,000 new residential customers.